Steel column installation results depend on three decisions made before the first crane lift. First, is the anchor bolt survey complete? Second, does the leveling method match the column load and foundation detail? Third, is grouting planned at the bay level rather than column by column? The lifting steps that follow are mostly mechanical. What prevents stoppages and rework is how well each of these three areas is prepared.
At Xinguangzheng, we design, fabricate, and install steel structures — from individual metal building components through complete industrial, warehouse, and commercial frames. This guide covers what project teams need to check at each phase — from anchor bolt review through grouting and final acceptance. If your project is near the anchor bolt or base plate design stage, share the structural drawings with us early. Catching tolerance problems before concrete is poured is far easier than fixing them after.
Anchor Bolt Verification Before Column Delivery
Survey anchor bolt position, elevation, and thread projection before any steel column is delivered to site. Confirm all measurements against the structural drawings. AISC and ACI 117 use different tolerance tables, and the two standards do not fully line up. AISC limits for bolt group position and plumb are tighter than ACI 117 limits. The only item both standards agree on directly is top elevation. The ASCC (American Society of Concrete Contractors) has noted that this gap causes disputes at the concrete-to-steel interface. Contract documents should state which standard governs before foundation work starts.
Where the foundation is built to ACI 117 tolerance but the steel frame follows AISC requirements, check that actual bolt positions meet the AISC limits before fabricating base plates. The hole pattern in the base plate is sized around a specific assumed tolerance range.
Three survey items need recorded measurements at every column location before delivery:
- Plan position: Measure the distance from each bolt group center to the column grid point in both axes. Deviations beyond the base plate hole tolerance cannot be fixed in the field without written approval from the structural engineer of record (SER).
- Top elevation and thread projection: Bolt top elevation sets the working height for leveling nuts. Too little thread projection leaves no room to adjust. Too much can conflict with the column shaft. Confirm the required projection from the base plate detail before concrete is poured.
- Plumb of individual bolts: A bolt that looks plumb at the surface may angle below and place its thread at the wrong position at plate level. Check plumb along the full visible length, not just at the top.
Any anchor bolt repair, replacement, or field change requires written SER approval before that column is erected. Under OSHA 29 CFR 1926.755, the controlling contractor must also notify the steel erector in writing of any bolt changes before columns are set. We treat this as a hold point — no column is set at a location with a recorded bolt change without written SER approval in hand.
Choosing a Leveling Method: Nuts, Shims, or Plate
The right leveling method depends on three things: the erection load the column carries before grouting, whether the anchor rods are designed for the load path each method creates, and the grout space under the base plate. Foundation elevation accuracy also plays a direct role — see our guide on leveling the building site for preparation requirements before columns arrive. Several erection guides claim leveling nuts are always the best choice. This is not accurate. On heavily loaded columns where the anchor rod design did not account for the erection compression case, using leveling nuts can create a problem.
| Leveling Method | Load Path Before Grouting | Adjustment Range | Suited For | Key Constraint |
|---|---|---|---|---|
| Leveling nuts on anchor rods | Through anchor rods in compression — an unusual load case for rods normally designed in tension | High — height adjusts by turning the nut | Columns with lighter erection loads where anchor rods have been checked for the compression case; where grout space fits nut height | Check anchor rod compression capacity at the footing before using this method on heavily loaded columns. AISC Design Guide 1 recommends limiting it to columns with relatively light erection loads. |
| Steel shim packs | Direct bearing — shims carry compression load to the foundation without loading the anchor rods | Moderate — limited by shim stack height and stability | Most standard industrial frame columns; widely used where elevation variation is within the range of stacked steel plate (illustrative; confirm against project foundation tolerance) | Shim stacks must be stable before grouting; wedges can help. Per common project specifications and AISC guidance, shims stay in place after grouting — removal is not required. |
| Pre-grouted leveling plate | Bearing on a pre-set grout pad — no anchor rod compression during erection | Very low — set by plate placement during foundation work | High-precision jobs such as crane runway columns or equipment support columns; projects with tight elevation control during concrete work | No adjustment after placement. Foundation elevation must be tightly controlled. Recheck elevation after the plate is set and before concrete cures. |
Confirm the leveling method for each column type from the structural drawings and erection plan before columns arrive. This is not a decision for the erection crew to make on the day of setting. When the method is not clearly stated in the contract documents, erectors use whatever material they have on hand. That may not match the anchor rod design or the grout space under the plate.
On projects where leveling nuts are specified for columns with large erection loads — for example, the first columns in a heavy industrial frame that will carry several floors of steel before grouting — we check that the anchor rod design includes a compression case review at the footing. If the rods were designed only for tension under wind or seismic loads, routing erection load through leveling nuts adds a compression demand the design did not include. Finding this before columns arrive lets us update the erection plan to use shim packs instead — without delaying the crane schedule.
The Plumbing Measurement Mistake on Tall Columns
Plumb measurement errors often come not from using the wrong tool, but from reading at the wrong time. On tall columns with large exposed flanges, solar radiation hits one face harder than the other. This creates a temperature difference across the section. The warmer face expands, and the column bows slightly toward the shaded side. This is thermal movement. It is not a column defect, and it is not a tolerance item in erection standards. If you correct a thermally bowed column, the fix may become wrong once the column cools and straightens.
This effect appears on tall columns with large exposed flange areas in direct sun, mostly from mid-morning to mid-afternoon. The right response is to take plumb readings early in the morning, before the sun heats one face more than the other. Another option is to take readings at several times of day and separate the thermal movement from the true geometric deviation before making any correction. Write this measurement timing requirement into the project erection plan — do not leave it to field judgment.
Regardless of sun conditions, always use a total station, digital theodolite, or laser plumb device to check column plumb. A spirit level or plumb bob is not acceptable for structural columns. Measure in two perpendicular axes. Apply corrections in both directions before accepting the reading. The allowed deviation is in the project contract documents — there is no single value that applies to all projects. Use a come-along or turnbuckle guy wire to apply controlled lateral force when making corrections. Do not lock the column in place until plumb is confirmed by instrument in both axes and recorded.
Lifting, Setting, and Temporary Bracing
Attach column rigging through a bolt hole in the web near the top, through a fabricated erection lug, or via a choker sling with a positive stop to prevent sliding. Confirm crane capacity at the actual lift radius — not the nameplate maximum — and record it in the lift plan. For single columns, use the rotation method to lift from horizontal to vertical. Keep the crane line above the pick point throughout to control swing. Once the column is vertical and the crane holds the full load, pause to let the load settle before moving the column over the anchor bolts.
Once the base plate contacts the shims or leveling nuts, install all anchor bolt nuts and washers right away — not only the ones that are easy to reach. OSHA 29 CFR 1926.755 requires all columns to be anchored with at least four anchor rods. It also requires a competent person to decide whether guying or bracing is needed. If it is needed, it must be installed. Crane release is allowed only after the column reaches the temporary stability required by the erection plan and that competent person’s evaluation. A column on anchor bolts alone — with no guying and no connection to adjacent structure — may not be stable under wind load. The erection plan must define the bracing requirement for each column type before site work starts. This is not decided at the crane on the day of erection.
For frame bent lifts — where multiple columns and beams are assembled on the ground and lifted as a unit — rig the load to pick balanced and level. Apply the same four-rod engagement and bracing check at each column base. Confirm temporary bracing before releasing rigging at any column in the bent.
When erection crews work under crane schedule pressure — especially when the crane is shared with other trades — the bracing decision can shrink to a quick conversation rather than a planned review. On a multi-bay warehouse frame we reviewed, a corner column was released with only two nuts hand-tight and no guying. Wind that day rotated the base enough to stretch one anchor rod. The repair required SER approval and set back the erection sequence across the bay. The pattern is consistent: the bracing plan must be in writing before mobilization, not worked out on site as columns go up.
Base Plate Grouting: Timing and the Bay Rule
Plan grouting at the bay level, not column by column. Once grout reaches its specified cure strength, the column position is locked. If a later survey finds a plumb error in one column after nearby columns are already grouted, fixing the ungrouted column means working around the locked positions. Fixing a grouted column means cutting through the grout bed. That is slow and destructive, and it requires SER review before the column can be reset. Per the AISC Code of Standard Practice and standard project erection plans, no base plate should be grouted until all columns in the erection sequence are aligned and plumbed. The erector must be able to adjust columns during this process.
The bay-level grouting sequence in practice:
- Set all columns in the bay, plumb each by instrument in both axes, and secure with temporary bracing or guying.
- Run a full instrument survey of all columns in the bay. Fix any plumb deviations before placing any grout.
- Confirm the grout type from the structural drawings. Non-shrink cementitious grout is standard for most structural building columns — it does not shrink during curing, unlike ordinary cement grout. Use epoxy grout where high bond strength, chemical resistance, or resistance to dynamic loads from equipment is required — typically crane columns, precision equipment supports, or structures exposed to chemical spill. The structural engineer selects the grout type. It is not a field decision.
- Push grout in from one side of the base plate. Keep going until it comes out the other side — this confirms full fill. For larger base plates, AISC Design Guide 1 recommends considering grout holes when the shorter plate dimension exceeds about 24 inches (610 mm). One or two holes allow filling from above and prevent air pockets.
- Leave shims and leveling nuts in place after grouting. Per common project specifications and AISC guidance, removal is not required. Compressive load distributes between the shims and grout, and the assembly works as designed. If the project documents call for shim removal or flush-cutting, confirm that with the SER before grouting.
- Do not load the column until the grout meets both the manufacturer’s minimum cure time and the project specification strength. Loading too early risks crushing the grout bed and shifting the column position.
Acceptance Criteria Before Beam Connections
Check and record four items against the project tolerance requirements before beam connection work begins on any column in the bay. Skipping this step under schedule pressure is one of the most common causes of frame geometry problems in multi-bay industrial buildings. Once beam connections lock adjacent columns in place, small errors grow across bays.
The four items are: column plumb in both axes, measured by instrument from base to splice or top of shaft; top-of-column elevation, surveyed against the structural drawing datum; anchor bolt nut tightening condition per the project specification or the engineer of record’s direction — the required condition, whether snug-tight, pretensioned, or other, is defined in the project documents, not by a standard torque value; and grout cure, minimum strength per the grout data sheet or project specification, whichever is stricter. Record all four in writing. Verbal confirmation is not acceptable for structural acceptance.
In multi-storey frames, column splices usually sit one to two floor levels above the beam connection point. The column spans two or three storeys and splices clear of the primary joint. Each splice tier needs the same plumb and elevation check before the next tier is delivered. We treat a documented instrument survey at every splice level as a hold point in the erection ITP before the next delivery leaves our facility.
Applicable boundary note: This guide applies to standard industrial and commercial steel frame columns on concrete foundations under normal gravity and lateral loading, with base plate connections designed as pinned or fixed. It does not cover seismically isolated structures, columns on elevated steel transfer frames, blast-resistant construction, chemically aggressive environments, moment-resisting base plates with thick stiffened plates, or projects governed by standards other than AISC. All tolerance values in this guide are illustrative. The governing values for any project are those in the IFC drawings, project specification, and approved erection plan.
Common Steel Column Erection Mistakes
Mobilizing before the anchor bolt survey is done. This is the most preventable cause of first-day delays. The survey takes a few hours. Finding an out-of-tolerance bolt group after the crane and crew are on site turns a short preparation task into an engineering problem requiring SER review and possible foundation repair. We do not release column deliveries until the survey is reviewed and all locations are confirmed within the governing tolerance.
Grouting columns before the bay survey is complete. Grouting locks position. The right approach — per AISC Code of Standard Practice and standard ITP practice — is to align and plumb all columns in the sequence before grouting any of them. On a large bay, this means holding grout on the early columns while the rest are still being plumbed. Then run one full bay survey before grouting starts. Teams that grout each column right after plumbing it often lock in small errors that only become visible after the full bay is measured together.
Removing shims after grouting. Many crews believe shims must come out after grouting to avoid a stress concentration. Per AISC guidance and standard project specifications, shims stay in place. The load shares between the shims and grout, and the assembly works as designed. Removal adds cost and risks disturbing the grout bed. If the project specification calls for removal or flush-cutting, follow that instruction and confirm it with the SER before grouting.
Using leveling nuts on heavily loaded columns without checking the design. For columns with lighter erection loads where the anchor rod design has been checked for the compression case, leveling nuts work well and are widely used. For heavily loaded columns — especially the first multi-storey columns carrying several floors of steel before grouting — the erection compression load may exceed what the rods were designed for. AISC Design Guide 1 recommends limiting the leveling nut method to columns with relatively light erection loads. Confirm the leveling method for each column type in the erection plan before columns arrive.
Loading a frame before grouting is complete. A CROSS safety report (CROSS-UK, Report ID 1190) described a case where a steel frame was loaded with pipe and cable racks before base plate grouting was done. The anchor bolts were not designed to carry the resulting compression and lateral loads in the ungrouted state. The approved drawings required grouting before loading. The contractor’s method statement did not enforce this. The standard fix is a documented ITP hold point with written sign-off before any trade is allowed to load newly erected steel.
Conclusion
Steel column installation depends on three things confirmed before the first lift. First, foundation readiness — anchor bolt positions surveyed against the governing tolerance, with elevation and projection measured and recorded. Second, leveling method confirmed against the column erection load and anchor rod design, not defaulted to whatever is most convenient. Third, grouting planned at the bay level, with hold points that stop subsequent trades from loading the steel before it is ready. A gap in any one of these creates a site problem that needs engineering review to fix. For a broader overview of the full steel building erection sequence, including site preparation and frame assembly, see our complete build guide.
As a steel building manufacturer working across industrial and commercial frames, we see preparation failures follow the same patterns. The anchor bolt survey is deferred most often — pushed until the erection crew is on site, at which point a bad bolt group stops all work while the SER is contacted. The bay-level grouting rule is misunderstood most often — erectors who grout each column right after plumbing lock in small geometry errors that only appear once the bay survey is run. On multi-storey frames, both errors compound. Catching a plumb error at the first splice level is a simple leveling fix. Catching it at the third level, with grouted bases and connected beams already in place, is a structural remediation that works back through every connection made since.
If your project is in the pre-erection phase, share your structural drawings and foundation survey data with us before columns are released for fabrication. We check anchor bolt tolerance against the base plate hole pattern, confirm the leveling method matches the anchor rod design, and set up the bay-level grouting sequence and ITP hold points before any steel leaves our facility. Reach out with your drawings and erection timeline to start that review.
FAQ
OSHA 29 CFR 1926.755 requires at least four anchor rods per column as a baseline for erection stability. The structural engineer may require more based on base moment, shear, and connection type. The structural drawings govern both number and layout. Any repair, replacement, or change to anchor rods after concrete is placed requires written SER approval before the column is erected. The controlling contractor must also notify the steel erector in writing of any such change.
Yes, in most cases. Per AISC guidance and standard project specifications, shims stay in place after grouting and do not need to be removed. The shims and non-shrink grout share the compressive load. The assembly performs as designed. Removing shims adds cost without structural benefit and can disturb the grout bed. If the project specification or drawings require removal or flush-cutting, follow those instructions and confirm with the SER if there is any question.
Grout after all columns in the erection sequence are aligned and plumbed — not before. Per the AISC Code of Standard Practice and standard erection plan requirements, do not grout individual columns while adjacent ones in the same sequence still need adjustment. The correct sequence is: set all columns in the bay, run the full plumb survey, make corrections, complete the acceptance check, then grout all base plates. Grouting each column right after plumbing it risks locking in small errors that only show up once the full bay is measured.
If plumb readings shift through the day on sun-exposed tall columns, the cause is usually thermal movement, not a column defect. Sun heats one face of a wide-flange section more than the other, and the column bows toward the shaded side. This is a field-observed effect, not a codified tolerance item. On columns with large exposed flanges in direct sun, take plumb readings in the early morning before the sun heats one face. Or take multiple readings through the day and assess before making corrections. Write the measurement timing requirement into the project erection plan.
The structural drawings and project specification define the grout type — it is not a field choice. Non-shrink cementitious grout is standard for most structural building columns. “Non-shrink” means it does not decrease in volume during curing, unlike ordinary cement grout. Epoxy grout is used where high bond strength, chemical resistance, or resistance to dynamic loads from equipment is required — typically crane columns, equipment supports, or structures in chemically aggressive environments. Meet both the grout compressive strength requirement and the minimum cure time before applying any structural load. Use the stricter of the grout data sheet and the project specification.
You need at least: issued-for-construction structural drawings, fabricator shop drawings with as-built records, the anchor bolt survey confirmed within the governing tolerance, the erection plan with the temporary bracing scheme and bay-level grouting sequence, and the lift plan with crane capacity confirmed at actual lift radii. For columns with field-welded base plate connections, the approved weld procedure specification and welder qualification records must be on site before welding starts. The most common gap that stops work on day one is starting without a complete anchor bolt survey or a written erection plan.
Still have questions?Ask our engineer directly — free advice, reply within 2 hours.
WhatsApp an Engineer




